Wind NAMA in Vietnam
Description
Overview | |
---|---|
Sector | Energy |
Focus area | Renewable energy (wind) |
Type of action | Strategy/Policy |
Scope | National |
Stage | Under development |
Submitted to UNFCCC registry | Yes |
Start of initiative | 2015 |
Financing and support details | |
---|---|
Financing status | Seeking financing |
Total cost | US$ 34 mln |
Financing requested | US$ 34 mln |
Financing received to-date |
(no data)
|
Principal source of financing | Multilateral |
Principal type of financing | Grant |
Capacity building required | Yes |
Technology transfer required | Yes |
Additional information | |
---|---|
Proponent(s) | Ministry of Industry and Trade (MOIT), Insitute of Meteorology Hyrdrology ad Envrionment (MONRE) |
International funder(s) | UNEP |
Organization providing technical support |
(no data)
|
Contact |
(no data)
|
The objective of the NAMA is to promote wind energy by removing barriers on policy, capacity and technology.
Activities: (2016 - 2030)
- Enhance the collaboration and the engagement of relevant ministries to development wind power development;
- Improve the support for investment progress of wind projects.
The NAMA has two phases of implementation: 2016-2020 and 2021-2030. The target is to achieve the share of wind power around 0.7% and 2.4% of total electricity in 2020 in 2030 respectively.
Ouputs incude:
- Develop a policy framework to support specific to wind power development in Vietnam
- Implement capacity building support for wind power development
- The technical barriers are eliminated through the development of instrumentation wind energy potential proposals for supporting the development of technical infrastructure and system maintenance repair wind power technology
- Pilot implementation a wind power project with a planned capacity of 5 MW grid connected and build MRV system for wind power development"
- Enhance the collaboration and the engagement of relevant ministries to development wind power development;
- Improve the support for investment progress of wind projects.
The NAMA has two phases of implementation: 2016-2020 and 2021-2030. The target is to achieve the share of wind power around 0.7% and 2.4% of total electricity in 2020 in 2030 respectively.
Ouputs incude:
- Develop a policy framework to support specific to wind power development in Vietnam
- Implement capacity building support for wind power development
- The technical barriers are eliminated through the development of instrumentation wind energy potential proposals for supporting the development of technical infrastructure and system maintenance repair wind power technology
- Pilot implementation a wind power project with a planned capacity of 5 MW grid connected and build MRV system for wind power development" cannot be used as a page name in this wiki.
Impact and MRV
|
Cumulative GHG reductions: 66.6 MtCO2e |
---|
No information has been provided on mitigative capacity
Co-benefits:
Social: |
* Reduced costs associated with air pollution (healthcare and environmental)
|
|
Economic: |
* Job creation
|
|
Environmental: |
* Improved local air quality
|
MRV Framework:
It is advised not to establish a new monitoring system for the proposed NAMA, but to use the existing monitoring and reporting system available for CDM projects.