Thermal Power Project with Capacity and Efficiency Increase I - TTP Nikola Tesla – Unit B2

From NAMA Database
Jump to: navigation, search



Serbia.png
To edit this page, log in and click on "edit with form" above
Serbia

Description

Overview
Sector Energy
Focus area Energy efficiency
Type of action Project
Scope Sub-national
Stage Under development
Submitted to UNFCCC registry Yes
Start of initiative 2015
Financing and support details
Financing status Seeking financing
Total cost EUR 111 mln
Financing requested EUR 111 mln
Financing received to-date
(no data)
Principal source of financing Not known
Principal type of financing Not known
Capacity building required No
Technology transfer required No
Additional information
Proponent(s) Public Enterprise Electric Power Industry of Serbia
International funder(s)
(no data)
Organization providing technical support
(no data)
Contact Aleksandar Obradovic
Objective:

Decrease emission intensity of lignite thermal power plant

Activities: (2015 - 2019)
Restoration and modernization of a lignite thermal power plant with capacity increase of 47 MW. Adopted technologies include rehabilitation and modernization of the steam turbine, condensing plant and cooling system unit, boiler and auxiliary equipment (e.g., low/high pressure feed water heaters), as well as revitalization and improvement of the firing system and the combustion process by introducing "Low NOx" burners and increasing the efficiency of the old thermal units. The Project will be implemented in two phases - 1st in 2015 and 2nd in 2019. Each phase will take 6 months.

Impact and MRV

No Data Available.png
Cumulative GHG reductions: 5.3 MtCO2e
Mitigative capacity:

No information has been provided on mitigative capacity

Co-benefits:

Social: Improvement of quality of life for local population due to income increase
Economic: Economic development of the region and employment, energy security, reduce electricity imports
Environmental: Decrease local air and water pollution

MRV Framework:
No MRV plan has been defined